The Casino Gaming ( Approved Integrated Resort Development) ( Celebration Jamaica Development Limited) ( Amendment) Order, 2017
17th day of june, 2017; and (b) completed no later than the 14th day of february, 2020. (3) the construction of the second one thousand associated hotel rooms and ancillary facilities of the celebration jamaica development ird shall be? (a) commenced no
The Casino Gaming (Approved Integrated Resort Development) (Celebration Jamaica Development Limited) Order (Revocation) Order, 2019
17th day of june, 2017, and the construction of the second one thousand rooms to no later than the 15th day of august, 2022: and whereas, notwithstanding, such extension, the construction of the first one thousand rooms had not commenced up to, upon or a